Pilot program

Before series production, we are testing the station on a few real sites, with partners willing to learn alongside us.

Duration : 3 to 12 months depending on the site. A monthly check-in, a mid-term review and a final review.

Propose a site
Illustration: community meeting about the station project
Illustration. Photos of installed stations will be published with the pilot results.

Sites we're looking for

  • An existing water point (network, borehole, well, tank) with real demand
  • A motivated, reachable operator with an Android smartphone
  • Local backing: a local official, neighbourhood committee or NGO active in the area
  • A secure spot for the station and its solar panel

We provide

  • The station, its solar panel and battery
  • Installation and operator training (half a day)
  • The app, the dashboard and an initial set of customer cards
  • Maintenance for the whole pilot period
  • A shared data report: volumes, availability, revenue, faults

You provide

  • A symbolic cost contribution (10 to 20%), a sign of commitment on both sides
  • The site, the water and the operator
  • Honest feedback at each monthly check-in
  • Permission to publish a case study (anonymised if you prefer)

Success criteria, written before installation

  1. Station availability (share of days it served water)
  2. Litres dispensed per day
  3. Revenue collected, compared to the situation before
  4. Number of faults and time to repair
  5. User and operator satisfaction

What happens next?

At the end of the pilot, you choose: keep the station (purchase or lease-to-own, contribution deducted), switch to the managed service (fixed fee per station, no revenue sharing), or stop. In that case, we take the station back.

Where?

On-site pilots currently take place in Togo. Elsewhere, we begin with a video demo and a site assessment.